Cedar Creek Solar Farm

C A S E  S T U D Y

2.4 MW

System Size

5 Years

ROI Payback Period

3,822 MWh

Annual Energy Savings

2,702 t

CO2 Reduction

312

Homes Energy Use Per Year

SUMMARY

Velo is proud to announce the commissioning of our latest addition to the GreenPowerEMC portfolio of projects. Our 2.4MW solar farm in Winder, GA feeds into the portfolio of renewable projects which provide the EMC’s of Georgia with clean solar power to offer their customers.

Cedar Creek Solar Farm is one of three sister projects delivered by VeloSolar for this program in 2017. VeloSolar is happy to contribute to the shift towards clean, sustainable distributed generation throughout our home state.

This site presented a unique challenge to our engineers who had to navigate around shallow bedrock throughout the site. We were able to provide the expertise to bring this solar farm online on schedule and on budget.

PROJECT GOALS

  1. Drill through shallow bedrock to mount posts
  2. Commission before December, 2017

Velo Solar provided us with a professional, well-executed, turnkey solar energy solution. Any issues that came up were handled directly and rapidly. I would not hesitate to recommend Velo to anyone considering a large scale solar installation.

Greg Morin CEO, Seachem Laboratories Inc.

SCHEDULE A FREE CONSULTATION

Want to get in contact for a Free Consultation?

Name*
Velo Solar respects your time and inbox! Subscribe to Velo Solar updates and our team will send out emails periodically to keep you updated. We appreciate your interest in Velo Solar.
This field is for validation purposes and should be left unchanged.